UK energy market regulator Ofgem is considering whether to grant a penalty exemption for the joint venture (JV) developing the Eastern Green Link 1 (EGL1) subsea electricity superhighway due to a 16-month delay said to be caused by supply chain constraints. The 2 GW EGL1 HVDC multi-directional cable is being developed by National Grid Electricity Transmission (NGET) […]
ASTI Ofgem HVDC Delay Event Submission Requirements Document Scotland England Guidance Eastern Green Link Energy Networks East Lothian Hawthorn Pit County Durham Penalty Exemption Period Output Delivery Incentive
Supply chain constraints push back UK’s $3B subsea electricity superhighway by 16 months